TheJakartaPost

Please Update your browser

Your browser is out of date, and may not be compatible with our website. A list of the most popular web browsers can be found below.
Just click on the icons to get to the download page.

Jakarta Post

Casablanca overpass to be ready by September

Deputy Governor Basuki “Ahok” Tjahaja Purnama confirmed on Wednesday that construction of the elevated road connecting Kampung Melayu, East Jakarta, to Tanah Abang, Central Jakarta, would resume despite an incomplete audit

Sita W. Dewi (The Jakarta Post)
Jakarta
Thu, July 4, 2013

Share This Article

Change Size

Casablanca overpass to be ready by September

D

eputy Governor Basuki '€œAhok'€ Tjahaja Purnama confirmed on Wednesday that construction of the elevated road connecting Kampung Melayu, East Jakarta, to Tanah Abang, Central Jakarta, would resume despite an incomplete audit.

The Rp 900 billion (US$92.65 million) project has been halted since March pending an evaluation by the city administration and an audit by the Development Finance Comptroller (BPKP) and Supreme Audit Agency (BPK).

'€œThe contractor is currently waiting for heavy equipment from Taiwan. The delivery might take a month,'€ Ahok told reporters at City Hall.

The city administration suspended the project for evaluation because it was behind schedule. It had been scheduled to be finished by June 29.

Ahok said that the contractor needed the equipment to support its work in the Jl. KH Mas Mansyur area, which often sees traffic gridlock during busy hours.

'€œThey need the particular heavy equipment to support construction work in such a busy area,'€ he said, adding that '€œIt might take two months until the remaining work is completed.'€

The 3.5-kilometer road project has been divided into three sections, comprising Jl. Prof. Dr. Satrio, Jl. Casablanca and Jl. KH. Mas Mansyur. The project is 90 percent complete. Project contractor state-owned PT Istaka Karya confirmed that the company would resume the construction once the heavy equipment arrives.

'€œWe are going to resume the construction of the remaining 10 percent once the equipment arrives. We ordered the equipment from Taiwan a week ago and will probably arrive within a month. We need this particular equipment because Jl. KH Mas Mansyur is a narrow road,'€ project manager Firmansyah Ibnu said.

Firmansyah said that due to the characteristics of the road, the company would only work at night.

Istaka Karya expects to complete the project within two months and to put the finishing touches in September. '€œWe want to continue the construction while waiting for the audit by the BPK. We expect to complete the project immediately,'€ he said.

Istana Karya is one of several construction companies that won tenders to construct the elevated road, which was initiated by then Jakarta governor Fauzi Bowo in 2010.

The city administration allocated Rp 64 billion from the 2013 budget to complete the section of the elevated road above Jl. Mas Mansyur.

Your Opinion Matters

Share your experiences, suggestions, and any issues you've encountered on The Jakarta Post. We're here to listen.

Enter at least 30 characters
0 / 30

Thank You

Thank you for sharing your thoughts. We appreciate your feedback.