TheJakartaPost

Please Update your browser

Your browser is out of date, and may not be compatible with our website. A list of the most popular web browsers can be found below.
Just click on the icons to get to the download page.

Jakarta Post

PLN struggles to resolve power crisis in N. Sumatra

State-owned electricity company PT PLN says that additional power supplies from existing and new power plants should resolve the acute power shortages in North Sumatra

Raras Cahyafitri (The Jakarta Post)
Jakarta
Sat, March 15, 2014

Share This Article

Change Size

PLN struggles to resolve power crisis in N. Sumatra

S

tate-owned electricity company PT PLN says that additional power supplies from existing and new power plants should resolve the acute power shortages in North Sumatra.

PLN senior corporate communications manager Bambang Dwiyanto said on Friday that the additional supplies were expected to come from the Asahan hydropower complex and the Nagan Raya coal-fired power plant (PLTU), which is now under construction.

Additional supplies would also be provided by the Belawan GT 2.2 combined-cycle power plant (PLTGU) and the Labuhan Angin PLTU, which were currently undergoing maintenance, he said.

The company has been criticized for its failure to resolve the shortage of electricity in the North Sumatra area, where supplies of power can no longer meet the growing demand.

PLN hopes the Asahan power plants, which are owned by PT Indonesia Asahan Aluminum (Inalum), will be able to increase their output to 135 megawatts (MW) from 90 MW at present, while the Belawan PLTGU is expected to provide 180 MW, Labuhan Angin PLTU 75 MW and Nagan Raya PLTU a further 60 MW.

The repair work on the Belawan PLTU was supposed to have been completed by last month, he said. '€œWe missed the target for work at Belawan. There are a number of adjustments still needed. Nagan Raya is expected to be ready this month,'€ Bambang said.

The government recently took over Inalum from a consortium of Japanese companies after their contract to run the company expired.

The peak electricity demand in the northern part of Sumatra amounts to 1,650 MW, according to Bambang. However, PLN is only able to supply around 1,400 MW.

The company has hired diesel generators since last year in order to provide an additional 150 MW. However, as of last year they had only been able to provide 20 MW.

 '€œThe diesel power will be generated gradually starting from April to June 2014,'€ Bambang said.

According to usual practice in electricity supplying, PLN ought to provide a 30 percent margin of reserves in order to avoid blackouts when disruptions occur.

In its attempt to generate the necessary reserve margin in the future, PLN is betting on the development of the Pangkalan Susu PLTU, which is designed to have a capacity of 2x200 MW and is scheduled to be in operation by year-end.

The development of the Pangkalan Susu plant is progressing well, but there have been problems with the acquisition of land for sites for transmission towers.

Land acquisition has often hampered infrastructure development in the country. The development of a 2,000 MW power plant in Batang, Central Java, has also been delayed for this reason.

Your Opinion Matters

Share your experiences, suggestions, and any issues you've encountered on The Jakarta Post. We're here to listen.

Enter at least 30 characters
0 / 30

Thank You

Thank you for sharing your thoughts. We appreciate your feedback.