TheJakartaPost

Please Update your browser

Your browser is out of date, and may not be compatible with our website. A list of the most popular web browsers can be found below.
Just click on the icons to get to the download page.

Jakarta Post

Jakarta-Bandung high-speed railway project focuses on 'critical spots'

Forty-two points were under construction, including seven tunnels and a train depot in Tegalluar, Bandung.

Riza Roidila Mufti (The Jakarta Post)
Jakarta
Fri, May 3, 2019

Share This Article

Change Size

Jakarta-Bandung high-speed railway project focuses on 'critical spots' A worker cleans debris at the construction site of a giant tunnel for the Jakarta-Bandung high speed railway in Walini, West Bandung regency, West Java recently. (The Jakarta Post/Wienda Parwitasari)

T

he construction of the Jakarta- Bandung high speed railway will focus on critical spots, such as tunnels, including the main tunnel in Halim, East Jakarta. 

State-owned construction firm Wijaya Karya (Wika) president director Tumiyana said construction and land acquisition had reached 15.03 percent and 96 percent completion, respectively.

“We project that this year, we’ll be able to complete 60 percent of construction,” Tumiyana told the press after the company’s shareholders meeting in Jakarta, recently.

Construction of the 142.3-kilometer project is currently focusing on its tunnels, including the main tunnel in Halim, which is 1,885 meters long.

The railway project will have 13 tunnels, seven of which have started their excavation phase. Walimi in West Java was another critical spot for the project because the developer had to construct three tunnels with a total length of 7.44 kilometers.

Wika corporate secretary Puspita Anggraeni said the project had been divided into 115 development points, 32 of which were elevated projects, including bridges in Bekasi, West Java.

Puspita said 42 points were under construction, including seven tunnels and a train depot in Tegalluar, Bandung.

She added that another 41 points were being prepared for the next construction phase.

The high speed train is designed to travel at a speed of 350 km per hour, about a 45-minute trip from Jakarta to Bandung.  The developer aims to complete construction of the entire project by June 2021, a two-year delay from its original plan. (bbn)

 

Your Opinion Matters

Share your experiences, suggestions, and any issues you've encountered on The Jakarta Post. We're here to listen.

Enter at least 30 characters
0 / 30

Thank You

Thank you for sharing your thoughts. We appreciate your feedback.