Smelters likely to be finished late because of lockdowns: Freeport

Norman Harsono (The Jakarta Post)
Jakarta
Fri, August 28, 2020 Published on Aug. 27, 2020 Published on 2020-08-27T13:46:40+07:00

Change text size

Gift Premium Articles
to Anyone

Share the best of The Jakarta Post with friends, family, or colleagues. As a subscriber, you can gift 3 to 5 articles each month that anyone can read—no subscription needed!
Smelters likely to be finished late because of lockdowns: Freeport Operations are ongoing at mining firm PT Freeport Indonesia in Timika, Papua. (Courtesy of/PT Freeport Indonesia)

T

he development of two metal smelters by gold and copper mining firm PT Freeport Indonesia (PTFI) has fallen well behind schedule because of the pandemic-related lockdowns. The company expects them to come onstream one year late.

The copper concentrate smelter – one of only two being developed in Indonesia – reached a 5.9 percent completion rate in July, below the targeted 10.5 percent, according to the Energy and Mineral Resources Ministry’s mining director general, Ridwan Djamaluddin.

Meanwhile, the company’s gold and silver smelter had reached 9.79 percent completion, below the 14.3 percent target, he said during a hearing with House of Representatives legislators and Freeport Indonesia on Thursday.

The government, he continued, expected Freeport to finish construction by 2023, despite the company’s previous requests to extend the deadline to 2024, as the new Coal and Mineral Mining Law mandates all metal ore must be processed domestically by 2023.

“We will follow the prevailing law,” Ridwan said.

Freeport deputy president director Jenpino Ngabdi stated on Thursday that project contractors based abroad were unable to finish project designs, finalize prices and procure equipment due to international lockdowns.

“Due to COVID-19, delays have been ongoing for around nine months,” he said. “We ask to be given a relaxation to complete the smelter in 2024.”

Freeport Indonesia has disbursed $290 million for the smelters as of July, mostly for land clearance. The combined investment value for the two smelters is $3 billion.

The projects, both located in Gresik, East Java, are among dozens of smelters being developed in Indonesia as the country, which relies heavily on mining for export revenue, ramps up plans to downstream the mining industry.

Read also: Jokowi reaffirms Indonesia’s 'massive downstreaming’ of natural resources

In May, Freeport also stated that it would operate the Grasberg mine in Papua, the world’s biggest gold mine, with a “skeletal team” after a rise in coronavirus infections in the area, according to Reuters report.

Your Opinion Matters

Share your experiences, suggestions, and any issues you've encountered on The Jakarta Post. We're here to listen.

Enter at least 30 characters
0 / 30

Thank You

Thank you for sharing your thoughts. We appreciate your feedback.

Share options

Quickly share this news with your network—keep everyone informed with just a single click!

Change text size options

Customize your reading experience by adjusting the text size to small, medium, or large—find what’s most comfortable for you.

Gift Premium Articles
to Anyone

Share the best of The Jakarta Post with friends, family, or colleagues. As a subscriber, you can gift 3 to 5 articles each month that anyone can read—no subscription needed!

Continue in the app

Get the best experience—faster access, exclusive features, and a seamless way to stay updated.