Eni's Geng North gas project to start in 2027, SKK Migas says

Fransiska Nangoy and Bernadette Christina (Reuters)
Jakarta
Wed, August 28, 2024 Published on Aug. 28, 2024 Published on 2024-08-28T19:01:39+07:00

Change text size

Gift Premium Articles
to Anyone

Share the best of The Jakarta Post with friends, family, or colleagues. As a subscriber, you can gift 3 to 5 articles each month that anyone can read—no subscription needed!
Eni's Geng North gas project to start in 2027, SKK Migas says SKK Migas chairman Dwi Soetjipto gestures during an interview at his office in Jakarta on Aug. 28, 2024. (Reuters/Ajeng Dinar Ulfiana)

I

ndonesia expects Eni's nearly US$12 billion Geng North gas project to start production in late 2027, among the fastest developments the country has ever seen, the head of its upstream oil and gas regulator told Reuters on Wednesday.

Speedy development of Geng North, discovered in 2023, is expected to be the model for future gas development in resource-rich Indonesia, following recent giant gas discoveries, Dwi Soetjipto, the chairperson of SKK Migas, said in an interview.

Last week, Indonesia approved Italian oil major Eni's development plans for Geng North as well as new plans for their nearby Gehem, Gendalo and Gandang fields, which are part of the Indonesia Deepwater Development (IDD) project that it acquired from Chevron last year.

To ease any bureaucratic delays, SKK Migas formed a team that worked directly with Eni on Geng North's development and design phase, Dwi said.

"There must be changes in the project execution mechanism. If this is successful, this can be a model for other projects," he said.

The project is also helped by the availability of an existing LNG plant in East Kalimantan, Dwi said, cutting back the time needed for development by three years.

Prospects

Every Monday

With exclusive interviews and in-depth coverage of the region's most pressing business issues, "Prospects" is the go-to source for staying ahead of the curve in Indonesia's rapidly evolving business landscape.

By registering, you agree with The Jakarta Post's

Thank You

for signing up our newsletter!

Please check your email for your newsletter subscription.

View More Newsletter

Eni will integrate the development of Geng North's 5 trillion cubic feet (Tcf) of gas with the Gehem gas project, creating the Northern Hub production area.

Gas from the Northern Hub's planned floating facility will be piped onshore through the East Kalimantan pipeline network, and liquefied at the Bontang LNG plant.

Eni did not immediately comment on the timeline Dwi said for Geng North's start up.

SKK is hopeful for a similar accelerated development timeline for the South Andaman block held by the United Arab Emirates' Mubadala Energy.

Development plans for the South Andaman gas project are expected to be approved late this year with production targeted to start in 2028, Dwi said.

"The work in South Andaman may be more complicated, they are both deep water, but there is no infrastructure yet for South Andaman," he said.

There is a possibility the project could utilize the Arun LNG plant in nearby Aceh province, but the obsolete plant may not be suitable for reactivation, he said.

Discoveries by Eni and Mubadala last year, among the biggest globally in 2023, has put Indonesia back on the map of energy explorers, Dwi said.

"Therefore the development of Geng North has a very strategic meaning for Indonesia's oil and gas in the future," he said.

"Indonesia is back to being an exploration destination."

Previously a member of the Organization of the Petroleum Exporting Countries, Indonesia's oil and gas output has declined as reserves deplete while new projects, such as INPEX's Abadi LNG plant, are yet to start up.

China's CNOOC, CNPC and Sinopec, as well as Malaysia's Petronas are among those conducting exploration in east Indonesia, Dwi said.

Eni has also said they are planning to conduct more drilling near its existing sites.

"In Geng North they believe there could be up to 14 Tcf (of gas) in that area," he said.

Your Opinion Matters

Share your experiences, suggestions, and any issues you've encountered on The Jakarta Post. We're here to listen.

Enter at least 30 characters
0 / 30

Thank You

Thank you for sharing your thoughts. We appreciate your feedback.

Share options

Quickly share this news with your network—keep everyone informed with just a single click!

Change text size options

Customize your reading experience by adjusting the text size to small, medium, or large—find what’s most comfortable for you.

Gift Premium Articles
to Anyone

Share the best of The Jakarta Post with friends, family, or colleagues. As a subscriber, you can gift 3 to 5 articles each month that anyone can read—no subscription needed!

Continue in the app

Get the best experience—faster access, exclusive features, and a seamless way to stay updated.