TheJakartaPost

Please Update your browser

Your browser is out of date, and may not be compatible with our website. A list of the most popular web browsers can be found below.
Just click on the icons to get to the download page.

Jakarta Post

PLN’s geothermal plants likely to miss deadline

State electricity company PT Perusahaan Listrik Negara (PLN) reveals that there are 13 geothermal power plant projects that are likely to miss development deadlines and are still stuck in exploration stages

Rabby Pramudatama (The Jakarta Post)
Jakarta
Thu, July 26, 2012

Share This Article

Change Size

PLN’s geothermal plants likely to miss deadline

S

tate electricity company PT Perusahaan Listrik Negara (PLN) reveals that there are 13 geothermal power plant projects that are likely to miss development deadlines and are still stuck in exploration stages.

PLN renewable energy chief Muhammad Sofyan said that partners responsible on the upstream production side were struggling with a variety of problems that slowed down the exploration process, ranging from a lack of supporting infrastructure to tough licensing procedures and financing.

“I am afraid if we don’t discuss the matter with our partners, all exploration phases will take longer than we expected,” Sofyan said.

According to the 2003 Geothermal Law, contractors are given three years to complete the exploration stages of a project with a possible two-year extension. All of project development deals were signed by PLN and partners in April 2010.

All of the geothermal power plant projects are intended to fulfill the second phase of the government’s electrification acceleration program known as the 10,000 megawatt (MW) fast-track program that was intended for completion in 2014.

Previously, the Energy and Mineral Resources Ministry’s director general of electricity, Jarman, said that most construction companies involved in the development of power plants under the first phase of the 10,000 megawatt (MW) fast-track program may be fined for construction delays.

Overall, the completion rate of the 10,000 MW project had topped 40 percent in July this year, Jarman said, adding that the rate was expected to increase to 60 percent by the end of the year.

One of PLN’s partners, Pertamina Geothermal Energy (PGE) — a subsidiary of state-owned oil and gas producer PT Pertamina — confirmed that it was facing problems in the exploration of geothermal sites for three PLN power plants.

The sites are located in Hulu Lais in Bengkulu, Sungai Penuh in Jami and Kotamobagu in North Sulawesi.

PGE corporate secretary Adiatma Sardjito told The Jakarta Post that the three projects were delayed due problems unique to the geothermal sites’ locations.

“On the Kotamobagu project, we have drilled two wells, however, the results have not been satisfactory as [the steam’s] pressure and temperature are not as good as we expected,” he said over the phone.

“We are now conducting another reservoir study to locate new wells in Kotamobagu.”

On the Sungai Penuh project, the lack of adequate roads had hampered the flow of construction vehicles to the project site, Adiatma said. There was no other solution apart from constructing a new road, he added.

Adiatama said the third project, in Hulu Lais, was hampered by what he described as a “tough process” for obtaining permits from the forestry agency and local governments.

According to Sofyan, the problems troubling PGE also posed challenges for other partners on the remaining 10 geothermal projects — the Lumut Balai power plant in South Sumatra, Lahendong units 5 and 6 in North Sulawesi, Karaha Bodas unit 1 in West Java, Kamojang unit 5 in West Java, Wayang Windu power plant in West Java, Dieng units 2 and 3 in Central Java, Patuha units 2 and 3 in West Java and Sarulla in North Sumatra.

Your Opinion Matters

Share your experiences, suggestions, and any issues you've encountered on The Jakarta Post. We're here to listen.

Enter at least 30 characters
0 / 30

Thank You

Thank you for sharing your thoughts. We appreciate your feedback.